Key takeaways
- Size each piece to the shingle exposure plus 2 inches of headlap โ for standard 5-inch exposure, that’s 7-inch-long step flashing.
- Nail the horizontal leg to the roof deck only, high and covered by the next piece. Never nail the vertical leg to the wall.
- Run pieces shingle-fashion from eave to ridge with at least 2 inches of overlap, and never substitute a continuous L-metal strip at a sidewall.
Step flashing is a set of individual L-shaped metal pieces โ one per shingle course โ woven into the roof wherever it meets a vertical wall, each one lapping the piece below by at least 2 inches. When every piece is sized to the shingle exposure and nailed to the deck (never the wall), the wall-to-roof joint stays dry for the life of the roof. When it’s rushed, that same joint is the leak that ruins drywall, rots sheathing, and gets you called back a year later.
What step flashing actually does
Where a sloped roof dies into a wall โ a dormer cheek, a second-story sidewall, a skylight curb โ water running down the wall has to be handed off to the roof without getting behind the shingles. A continuous L-shaped strip can’t do it, because it has no laps: GAF’s technical bulletin TAB-R-121 flatly says L-metal should not be used at these transitions “due to its propensity to leak.”
Step flashing solves it by breaking the flashing into individual pieces, each one lapping the one below like shingles do. One piece per course, every course. GAF’s own bulletin calls proper flashing “the single most important aspect of your new roof,” and notes that flashings aren’t covered under the manufacturer’s limited material warranty โ the liability lands on whoever installed it. For more on how this whole corner of the trade fits together, the For Roofers hub collects every pro guide on this site.
The same water-shedding logic applies at the roof’s edges โ for the matching eave and rake detail, see how to install drip edge the right way.
The pieces and the dimensions
The standard pre-bent piece is a 5-by-7-inch rectangle folded at 90 degrees: the 7-inch length is what matters. That 7 inches comes from a simple rule โ the piece must be the shingle exposure plus at least 2 inches of headlap. Standard 5-inch exposure gives 7 inches. GAF’s TAB-R-173 bulletin (2021) specifies 5 inches up the wall and 5 inches out onto the roof as the standard, and permits a smaller 4-by-4 piece only when a full 36-inch width of leak barrier runs up the wall-to-roof transition. Use the standard 5-inch size and you don’t need to memorize exceptions.
You can buy pre-bent pieces in galvanized steel, painted aluminum, or copper โ pre-bent step flashing is cheap enough that bending your own from trim coil only makes sense on odd walls or when you run short mid-job. Per the Western States Roofing Contractors Association’s standard detail, use a non-corroding metal โ minimum 24-gauge galvanized or 16-ounce copper.
Install it right, course by course

Start at the eave with a kick-out flashing โ a diverter piece that throws water off the roof edge and into the gutter instead of behind the siding. It’s the piece most crews skip, and it’s the reason so many sidewall leaks show up at the bottom of the wall.
- Set the first piece against the wall at the eave, the horizontal leg flat on the deck. The bend should sit snug in the corner where wall meets roof.
- Nail the horizontal leg to the deck only โ one or two roofing nails placed high on the piece, up-slope and close to the wall, so the overlapping piece above covers them. This is the rule that matters most: the WSRCA detail says fastening to the vertical surface is not recommended, because the roof and the wall move differently and a nailed wall leg either buckles the flashing or breaks the seal.
- Lay the shingle over it. The end shingle of the course should cover the flashing completely.
- Set the next piece 5 inches up โ at the same position on the next shingle, matching the shingle exposure โ so it overlaps the piece below by the 2-inch headlap. Repeat to the ridge.
- Leave the seal strip exposed. Set the bottom of each piece just above the shingle’s self-sealing strip so the next shingle seals fully across to the vertical leg. Covering the strip is a small thing that creates a big problem.
- Let the siding be the counter-flashing. Bring wall siding down over the vertical legs by at least 2 inches, but hold it 1 to 2 inches above the roof surface so water and debris drain off instead of wicking up.
Keep the shingle nails back from the wall while you work โ the same nail-line rules from the nailing pattern guide apply here: no fastener within 6 inches of the wall that could pierce a flashing piece below.
The mistakes that cause the callbacks
Nailing the vertical leg to the wall. It feels more secure. It guarantees a failure โ differential movement between wall and roof works the piece until it opens a gap or buckles a shingle course.
Using L-metal instead of stepped pieces. Faster to run one long strip. GAF says it leaks, and the 2026 repair data backs the stakes: replacing failed step flashing at roof-to-wall intersections runs $250โ$600 per repair (Modernize’s 2026 cost guide), and a full step-flashing install costs $7โ$12 per linear foot โ most of that is the labor of doing it right, not the metal.
Short headlap. The 2-inch minimum overlap exists because wind-driven rain rides up under every course. A 1-inch lap saves nothing and leaks in the first real storm.
Reusing old flashing on a re-roof. Old pieces are cut to the old shingle’s exposure. New architectural shingles are thicker and often dimensioned differently, so the headlap math changes. GAF’s bulletin advises new step flashing whenever possible โ and if a wall is already showing the warning signs of a failing roof, the flashing there is guilty until proven innocent.
Sealant instead of flashing. A bead of roofing cement across a wall joint is a temporary patch, not flashing. It cracks in the first heat cycle and leaves the next guy โ you โ to explain why the “repair” failed.
Frequently asked questions
Do you nail step flashing to the wall or the roof?
The roof deck only. Place one or two nails high on the horizontal leg, up-slope near the wall, so the next piece covers the nail heads. The vertical leg stays unnailed โ nailing it to the wall locks two surfaces that expand and move at different rates, which eventually buckles the flashing or breaks the seal.
Can you reuse step flashing on a re-roof?
You usually can’t, and shouldn’t. Old pieces are sized for the old shingle’s exposure, and they’re nailed down from the previous installation โ pulling them out without mangling them is nearly impossible. Budget for new flashing on every tear-off; it’s the cheapest leak insurance on the job.
How far should step flashing extend up the wall?
Per GAF’s published specs, a minimum of 5 inches up the wall and 5 inches out onto the roof, with each piece at least 2 inches longer than the shingle exposure. The WSRCA allows a 4-inch minimum, but building to the GAF spec leaves margin โ and the siding will cover the extra anyway.